How to Account for Construction Holdbacks in Ontario
Holdback accounting in Ontario means recording the full progress billing as revenue. Book the 90% you expect now as accounts receivable, and put the 10% construction holdback in a separate holdback receivable account. Similarly, if you hold back from subcontractors, record the 10% as a holdback payable. Clear each account when the owner releases the holdback after the lien period ends. Track HST on the holdback separately, because it usually isn’t payable until release.
Holdbacks are one of the easiest places for a contractor’s books to go wrong. Ten percent of every progress invoice sits unpaid for months. Since January 1, 2026, the Ontario Construction Act has required owners to release most of it each year, not just at job end. As a result, if your bookkeeping still treats holdback as one lump sum collected at completion, your receivables, cash flow and HST filings may all be off.
This guide shows how to account for holdbacks from both sides of the contract. It covers journal entries, tax and HST timing, and what the 2026 changes mean for your books.
What Is a Holdback in Construction?
A construction holdback is part of each payment that owners and contractors must keep back. It protects subcontractors and suppliers who might file a lien.
Under the Ontario Construction Act, there are two types:
- Basic holdback: 10% of the value of work and materials supplied under each contract or subcontract.
- Finishing holdback: 10% of work done after the contract reaches substantial performance.
For holdback accounting in Ontario, the key point is that holdback is not a penalty or a deficiency fund. Instead, it exists so that if a contractor doesn’t pay its trades, those trades have money to claim against.
For that reason, owners who want security for deficiencies typically negotiate a separate deficiency holdback in the contract.
How Holdbacks Work Under the Ontario Construction Act
Holdback runs through the whole payment chain. First, the owner holds back 10% from the general contractor. Next, the general contractor holds back 10% from each subcontractor, and each subcontractor does the same with its own trades.
Traditionally, release happened at the end of the project:
- The contract reaches substantial performance, and the payment certifier publishes a certificate of substantial performance.
- A 60-day lien period follows, during which subcontractors and suppliers can preserve a lien.
- If no one preserves a lien, or the parties resolve any liens, the owner pays the basic holdback.
- The finishing holdback follows the same pattern, with its lien period running 60 days from completion.
Holdback also works alongside the Act’s prompt payment rules. The owner must pay a proper invoice within 28 days, less the holdback. A contractor must then pay its subcontractors within 7 days of being paid.
Clean invoicing matters, because you calculate the holdback on each proper invoice. Reliable Ontario bookkeeping services keep those invoices, holdback amounts and payment dates lined up.
What Changed on January 1, 2026: Annual Release of Holdback
The 2026 amendments to the Construction Act (Ontario) made annual release of holdback the default:
- Within 14 days after each contract anniversary, the owner must publish a notice (Form 6). It states the holdback accrued in the past year and the payment date.
- A 60-day lien window follows the notice.
- If no one preserves or perfects a lien, the owner pays that year’s holdback between 60 and 74 days after the notice.
- Each contractor and subcontractor must then pass the released holdback down within 14 days of receiving it.
- Owners can no longer give a notice of non-payment of holdback.
For contracts signed on or after January 1, 2026, annual release starts on the first anniversary. However, contracts signed before 2026 follow transition rules and start annual release later, so check your contract date with your lawyer. Release at substantial performance and completion still applies; there’s just less holdback left by then.
For holdback accounting in Ontario, this means holdback receivables and payables now turn over every year on long projects. Track them by contract year, not just by job. File them with the invoices, payment records and WSIB clearances covered in our guide to payroll and subcontractor records for contractors.
How to Account for Holdbacks: The Contractor Side
The core rule of holdback accounting in Ontario is simple. When a client holds back 10%, that construction holdback is still revenue you’ve earned. However, it’s not collectible yet. Under ASPE, the standard most private Ontario contractors use, the holdback is not deferred revenue. It’s a receivable with a later due date.
For this reason, set up a separate holdback receivable account rather than leaving the full amount in accounts receivable. This keeps your AR aging accurate, so a 10% balance that’s legitimately 300 days old doesn’t look like a bad debt. If past holdbacks are still mixed into your AR, catch-up bookkeeping can reclassify them before year-end.
Example: You issue a progress invoice for $100,000 of work, plus 13% HST. The client holds back $10,000.
| Account | Debit | Credit |
|---|---|---|
| Accounts receivable | $101,700 | — |
| Holdback receivable | $10,000 | — |
| Construction revenue | — | $100,000 |
| HST payable | — | $11,700 |
The accounts receivable line is the $90,000 you’ll collect now, plus HST on that amount. You don’t record HST on the $10,000 holdback yet
When the owner releases the holdback:
| Account | Debit | Credit |
|---|---|---|
| Cash | $11,300 | — |
| Holdback receivable | — | $10,000 |
| HST payable | — | $1,300 |
If a lien is preserved or a dispute delays release, leave the balance in holdback receivable and note it. However, write it down only if collection becomes genuinely doubtful.
Holdback Payable: The General Contractor Side
If you hold back from subcontractors, holdback accounting in Ontario works in reverse. You need the mirror account: a holdback payable liability. In other words, this money isn’t yours. Under the Act, you hold the holdback owed to subcontractors in trust, so it shouldn’t be spent on other jobs or operating costs.
Example: A subcontractor invoices you $50,000 plus HST. You hold back $5,000.
| Account | Debit | Credit |
|---|---|---|
| Subcontract costs | $50,000 | — |
| HST recoverable (ITC) | $5,850 | — |
| Accounts payable | — | $50,850 |
| Holdback payable | — | $5,000 |
When you release it:
| Account | Debit | Credit |
|---|---|---|
| Holdback payable | $5,000 | — |
| HST recoverable (ITC) | $650 | — |
| Cash | — | $5,650 |
A strong accounts payable process should flag each holdback’s release date, especially now that annual releases must flow down to subtrades within 14 days.
GST/HST on Construction Holdbacks
HST is where holdback accounting in Ontario most often goes wrong, because tax on a holdback follows its own timing rule. This rule covers holdbacks under a written construction agreement or a provincial law like the Ontario Construction Act. Under CRA policy, tax on the holdback becomes payable on the earlier of:
- the day the holdback is paid, or
- the day the holdback period expires.
That’s why many contractors charge HST only on the 90% they collect now and bill HST on the holdback when it’s released. The same timing applies to input tax credits on the general contractor side: claim the ITC on the holdback portion when the tax becomes payable.
Whichever method your contracts use, apply it consistently. Charging HST on the full invoice in one month and on 90% the next makes your HST returns hard to reconcile.
Income Tax Treatment of Holdbacks
For income tax, however, holdbacks don’t always follow your accounting entries.
- Holdbacks receivable: The CRA has long allowed contractors to leave holdbacks out of income until they become receivable under the provincial statute. In general, that means once the payment certifier issues the required certificate and the lien period expires. If you defer, you must do so consistently from year to year.
- Holdbacks payable: Amounts you hold back from subcontractors are generally deductible only when they become payable under the Act, not when the subcontractor invoices.
With annual release, more holdback will become receivable and payable each year on long projects, so the deferral may shrink. Talk to your accountant before year-end, since these adjustments flow directly into your T2 corporate tax return.
Tracking Holdbacks: A Monthly Routine
Good holdback accounting in Ontario comes down to a few habits:
- Keep a holdback register for each contract and subcontract, showing contract date, anniversary date, holdback by period, released amounts and the balance.
- Reconcile monthly. Opening balance, plus new holdback, minus releases, should equal the ledger balance in holdback receivable and holdback payable.
- Diarize anniversaries. Each contract anniversary now triggers a notice, a lien window and a release date.
- Watch for liens. If a lien is preserved during a release window, hold the related amount and record why.
- Separate trust money. Report holdback payable clearly, and don’t let it fund other work.
Additionally, most accounting software can handle this. QuickBooks and Sage both support holdback or retainage tracking on invoices and bills, and our accounting software comparison covers the options.
Common Holdback Accounting Mistakes
Holdback errors are a construction-specific version of the bookkeeping mistakes small business owners make: small, routine entries that compound into a big problem by year-end.
- Leaving holdback inside accounts receivable, which makes AR look overdue and hides what’s actually collectible.
- Treating holdback as deferred revenue or ignoring it until the job ends.
- Charging or reporting HST on holdbacks inconsistently.
- Spending holdback payable on operating costs, even though it’s trust money.
- Missing the 14-day flow-down when annual holdback is released to you.
- Using holdback to cover deficiencies instead of a separate deficiency holdback.
Most of these mistakes come from treating holdback accounting in Ontario as a year-end task instead of a monthly one. If you spot any of them, fix them before your next HST filing or year-end close.
Final Thoughts
Construction holdback is earned money that arrives late, or money you owe that isn’t yours to spend. In short, keep it in its own accounts, track it by contract year and match HST to the release date. The 2026 annual release rules make that discipline more important, because holdback balances now move every year instead of once per project.
Contract terms and transition rules vary, so treat this guide as general information. Before you change how you handle holdback accounting in Ontario, talk to an accounting firm in Ottawa that works with contractors.
Get Help With Holdback Accounting in Ontario
HAT Accounting provides construction bookkeeping for general contractors and trades, including holdback registers, progress billing, HST and year-end reporting. If you’re looking for reliable bookkeeping in Ottawa, contact us for a free consultation.
FAQs
What is a holdback in construction?
It’s a portion of each payment, 10% in Ontario, that an owner or contractor keeps back to protect subcontractors and suppliers with lien rights. Owners release it once the lien period expires and no liens are outstanding.
Is a construction holdback revenue or a receivable?
Both. The holdback is part of the revenue you’ve earned, so you recognize it as revenue. However, because it isn’t collectible yet, you record it in a separate holdback receivable account until release.
When is holdback released in Ontario?
Under the 2026 rules, owners release most holdback annually. The owner publishes a notice within 14 days after each contract anniversary. Then a 60-day lien window follows, and the owner pays if no one preserves a lien. Finally, owners release the remaining holdback after substantial performance and completion.
Do I charge HST on the holdback?
HST on a holdback becomes payable on the earlier of the day it’s paid and the day the holdback period expires. Many contractors bill HST on the holdback when it’s released.
Can an owner keep holdback for deficiencies?
Holdback exists to protect lien claimants, not to fund deficiency repairs. Owners who want deficiency security usually negotiate a separate deficiency holdback in the contract.